Hotel room renovation costs in the United States can range from a few thousand dollars for a basic refresh to six figures for a luxury rebuild. The price depends on the work involved, the building’s condition, the location, and the hotel’s standards. Understanding the difference between a simple update and a full renovation helps you set a realistic budget before requesting contractor bids.
Quick Answer
For 2026 planning, a limited U.S. hotel room refresh may cost about $4,000 to $15,000 per key, depending on the property tier. A full room and bathroom renovation may range from roughly $8,000 to $150,000 or more. These are illustrative budgeting ranges, not verified national averages or contractor quotes.
Key Takeaways
- A soft-goods refresh costs less than replacing furniture, bathrooms, plumbing, and building systems.
- A per-key estimate is useful only when you know exactly which work and expenses it includes.
- Freight, permits, design, taxes, storage, room downtime, and contingency can add substantially to the initial estimate.
- Brand requirements, accessibility, building codes, and hazardous materials should be reviewed before bidding.
- A condition survey, model room, comparable bids, and phased construction plan help control renovation costs.
Average Hotel Room Renovation Costs by Type

Hotel room renovation costs differ by property category and project scope. Economy hotels usually need simpler materials and standardized furniture. Luxury hotels may require custom finishes, larger bathrooms, and complex installations.
The Nehmer and HVS Design 2026 Hotel Cost Estimating Guide, released May 19, 2026, separates renovation costs by hotel tier and project area. Its categories include guestrooms, bathrooms, corridors, public spaces, amenities, and infrastructure.
The publishers also provide access to the 2026 hotel cost guide through Nehmer’s request form. The guide is complimentary, although access requires submitting the form.
The following table provides broad planning bands for U.S. properties. These figures are illustrative estimates rather than published national averages or an exact reproduction of the 2026 guide.
| Hotel Segment | Limited or Soft-Goods Refresh | Full Room and Bathroom Renovation |
|---|---|---|
| Economy or limited service | About $4,000 to $10,000 per key | About $8,000 to $20,000 per key |
| Midscale or upper midscale | About $6,000 to $15,000 per key | About $15,000 to $35,000 per key |
| Upscale or upper upscale | About $10,000 to $25,000 per key | About $30,000 to $75,000 per key |
| Luxury, boutique, or resort | About $15,000 to $50,000 or more per key | About $60,000 to $150,000 or more per key |
Per key means per guestroom. However, contractors and consultants may use this figure for different scopes. One estimate might include only furniture and finishes. Another could include bathrooms, corridors, and shared building expenses.
A per-key cost is useful only when the scope behind that number is clearly defined.
Custom furniture, premium stone, plumbing relocation, structural repairs, and extensive bathroom work can push costs above the ranges shown. Reusing sound furniture, keeping plumbing in place, and standardizing materials may reduce costs.
Also, a renovation estimate is not the same as the cost of constructing a new hotel. New construction includes land-related development, structure, foundations, and other work that a normal renovation does not require.
What Counts as a Hotel Room Upgrade?
A hotel room upgrade can mean a simple cosmetic refresh or a complete reconstruction. Before comparing prices, define the work you want to complete.
Soft-Goods Refresh
A soft-goods refresh focuses on the appearance and comfort of existing guestrooms. Most walls, plumbing, wiring, and built-in furniture stay in place.
Common improvements include:
- Painting walls, ceilings, and trim
- Replacing carpet or installing suitable flooring
- Updating bedding and decorative textiles
- Replacing curtains, blinds, and window treatments
- Reupholstering serviceable furniture
- Updating artwork, lamps, and decorative accessories
- Making minor repairs to visible fixtures
This type of renovation usually causes less disruption than major construction. It works best when the room’s systems and built-in components remain in good condition.
Full Guestroom Renovation
A full guestroom renovation replaces more than cosmetic finishes. It may include beds, furniture, lighting, built-in cabinetry, technology, and selected electrical or mechanical components.
Typical work includes:
- Replacing mattresses, headboards, desks, and seating
- Installing new casegoods and closets
- Updating doors, hardware, and electronic locks
- Replacing televisions and related equipment
- Adding suitable charging outlets and controls
- Updating ceilings, walls, and flooring
- Replacing damaged millwork and built-in fittings
- Upgrading selected HVAC or electrical components
Ask whether the estimate includes demolition, furniture installation, freight, disposal, sales tax, and protection of occupied areas.
Guestroom and Bathroom Renovation
Bathroom renovation can add considerable expense because it involves several trades working in a small space. Plumbing, waterproofing, tile, ventilation, and electrical work often need careful coordination.
A complete bathroom renovation may include:
- Removing old fixtures, flooring, and wall finishes
- Replacing showers, tubs, sinks, and toilets
- Installing new waterproofing and tile
- Updating vanities, mirrors, and lighting
- Improving ventilation
- Repairing concealed water damage
- Making required accessibility improvements
- Relocating plumbing where the new layout requires it
Keeping plumbing fixtures in their existing locations can reduce demolition, piping, floor repair, and labor costs.
However, old or damaged plumbing should not be kept simply to reduce the initial budget.
Property Improvement Plan
A property improvement plan, or PIP, identifies upgrades a hotel brand requires. It is often part of a franchise agreement, renewal, transfer, or property review.
A PIP may include guestrooms and bathrooms, but it can also cover:
- Corridors and elevators
- Lobby and reception areas
- Breakfast rooms, restaurants, and bars
- Meeting spaces and business facilities
- Fitness centers and other amenities
- Exterior finishes and signage
- Parking and guest access areas
- Accessibility and life-safety improvements
- Technology and building infrastructure
Since a PIP can involve the entire property, its total cost may be much higher than a guestroom-only renovation.
Note: Before approving a budget, have a qualified hospitality designer, cost estimator, and appropriate licensed professionals review the property’s actual condition and requirements. Confirm whether each per-key figure covers guestrooms, bathrooms, furniture and fixtures, or the entire property improvement plan.
Factors That Influence Hotel Renovation Cost
Two hotels with similar room counts can have very different renovation budgets. The largest differences often come from their condition, location, materials, and required work.
- Project scope: Painting and replacing bedding costs less than rebuilding bathrooms or changing room layouts.
- Building condition: Water damage, old wiring, failing plumbing, damaged subfloors, and deferred maintenance increase expenses.
- Location: Local labor rates, contractor availability, permits, taxes, and transportation affect bids.
- Brand standards: Franchised hotels may require approved materials, furniture, technology, signage, and layouts.
- Room types: Suites, accessible rooms, connecting rooms, and different floor plans require separate measurements and quantities.
- Material quality: Commercial-grade standard products generally cost less than custom furniture, imported finishes, or specialty lighting.
- Building systems: Plumbing, electrical service, HVAC, fire alarms, sprinklers, and network infrastructure can add major expenses.
- Project schedule: Rush orders, weekend work, overtime, and expedited freight can raise costs.
- Operating conditions: Renovating an occupied hotel requires dust control, guest protection, noise management, and careful delivery planning.
Room size matters too. A larger suite generally needs more flooring, wall finishes, furniture, and labor than a standard guestroom.
Instead of relying on hotel star ratings alone, compare projects with similar room sizes, layouts, finishes, and construction requirements.
Breakdown of Common Hotel Renovation Costs
A complete hotel renovation budget should cover construction, furniture, professional services, logistics, and operational expenses. Leaving out any of these categories can make an estimate look artificially low.
The table below shows what each category may include.
| Budget Category | Examples |
|---|---|
| Preconstruction | Surveys, measurements, design, engineering, estimating, model rooms, testing, and brand review |
| Demolition and protection | Removal, waste hauling, dust barriers, floor protection, temporary partitions, and cleaning |
| Construction and finishes | Walls, ceilings, painting, flooring, tile, millwork, doors, hardware, and bathroom work |
| FF&E | Furniture, fixtures, beds, seating, desks, decorative lighting, window treatments, and artwork |
| MEP and technology | Mechanical, electrical, plumbing, HVAC, controls, locks, Wi-Fi, televisions, and fire systems |
| Permits and compliance | Permit fees, inspections, accessibility requirements, environmental reviews, and required testing |
| Procurement and logistics | Freight, receiving, warehousing, delivery, installation, taxes, damaged-product replacement, and spare stock |
| Operational impact | Rooms out of service, guest relocation, temporary facilities, security, signage, and extra housekeeping |
| Contingency | A controlled reserve for concealed damage, approved scope changes, and genuine project uncertainties |
FF&E means furniture, fixtures, and equipment. MEP means mechanical, electrical, and plumbing systems. Both categories may include substantial spending beyond visible room decoration.
Keep these costs separate in your estimates. This helps you identify missing items and compare contractor proposals accurately.
Economy Hotel Costs
Economy hotels usually focus on durability, simple room layouts, and practical finishes. Standardized materials can make purchasing and installation easier across many identical rooms.
A basic refresh may involve painting, flooring, bedding, curtains, lights, and selected furniture.
However, costs increase when the project requires:
- Complete bathroom replacement
- Damaged subfloor repairs
- Plumbing or wiring upgrades
- Replacement HVAC units
- New door and locking systems
- Accessibility improvements
Choose materials based on long-term performance, not purchase price alone. A cheap finish that needs frequent replacement may have a higher lifetime cost.
Upscale Hotel Expenses
Upscale hotels generally require more detailed finishes, higher-quality furniture, and additional guest amenities. Larger rooms and complex layouts can also increase material and labor requirements.
Expenses may include custom casegoods, upgraded mattresses, advanced lighting, premium flooring, acoustic treatments, minibars, and room-control technology.
Bathroom upgrades often involve more extensive tilework, better fixtures, improved lighting, and redesigned showers.
Owners should also address hidden problems before installing new finishes. Unresolved water leaks, HVAC failures, or electrical defects can damage completed work.
Luxury Room Investments
Luxury hotel renovations can involve custom furniture, natural stone, specialty lighting, advanced controls, premium textiles, and detailed millwork. Each custom item may require additional design, production, and installation work.
Luxury suites and resort rooms may also include:
- Oversized bathrooms and specialty showers
- Custom wardrobes and storage systems
- Premium artwork and decorative features
- Kitchenettes, kitchens, or private bars
- Fireplaces and specialty glazing
- Terraces and outdoor furniture
- Advanced entertainment and room controls
These features can push individual room costs far above standard hotel renovation ranges.
Include detailed shop drawings, material samples, factory inspections where needed, and receiving checks. Custom products can be expensive to replace if they arrive damaged or do not fit.
Hidden Costs That Cause Hotel Renovation Overruns
Hotel renovation budgets often exceed early estimates because important expenses were excluded. Some are predictable, while others become clear only after demolition.
Common overlooked costs include:
- Freight, fuel surcharges, receiving, and storage
- Sales or use taxes
- Demolition, waste removal, and disposal
- Night, weekend, or union labor
- Permit fees, engineering, and inspections
- Hazardous-material testing and abatement
- Dust barriers and temporary protection
- Replacement of missing or damaged products
- Spare parts and attic stock
- Lost contribution from unavailable rooms
- Guest relocation and recovery expenses
- Temporary utility shutdowns
- Additional accessibility or code work
- Brand-requested design changes
Room downtime deserves special attention. A room undergoing renovation cannot generate normal room revenue until it returns to service.
To estimate the impact, multiply the rooms unavailable by the affected nights and expected occupancy, then estimate the lost contribution after avoided variable expenses. Also account for any additional relocation or guest-service costs.
This approach is more useful than treating every unavailable room as a guaranteed full-rate booking.
Warning: A low contractor bid may exclude installation, freight, tax, permits, bathroom work, inspections, or temporary protection. Compare written scopes and exclusions before choosing the lowest price. An incomplete bid can result in expensive change orders.
Practical Cost-Saving Tips for Hotel Renovations

You can reduce hotel renovation expenses without sacrificing guest comfort or safety. The most effective approach is to control design decisions, purchasing, and scheduling before construction begins.
Effective cost control comes from defining the scope early, comparing equal bids, testing the design in one room, and limiting changes after procurement begins.
- Complete a condition assessment: Inspect guestrooms, bathrooms, plumbing, electrical systems, HVAC, waterproofing, doors, and safety equipment before estimating costs.
- Separate required work from optional improvements: Identify brand, code, safety, and maintenance needs before adding decorative upgrades.
- Standardize materials: Use consistent furniture, flooring, lighting, and fixtures across similar room types where practical.
- Reuse serviceable components: Refinish sound furniture or keep existing systems when their condition and expected life justify the decision.
- Plan purchasing early: Approve designs, samples, and shop drawings before releasing major orders.
- Request comparable proposals: Give every contractor the same specifications, quantities, drawings, and requirements.
- Control change orders: Require written pricing and authorization before changed work begins, except when immediate safety action is necessary.
- Apply value engineering carefully: Look for less expensive materials or construction methods without weakening durability, waterproofing, accessibility, or safety.
For example, using the same commercial-grade flooring across standard rooms may simplify ordering and reduce leftover materials. It can also make later repairs easier.
Similarly, a well-designed standard furniture package may cost less to maintain than several custom variations.
Pro Tip: Build and test one model guestroom before ordering furniture for the entire hotel. Ask housekeeping, maintenance, and operations staff to inspect it. Their feedback can reveal cleaning problems, damaged-prone finishes, awkward outlet positions, and maintenance issues before they affect every room.
Seasonal Trends for Planning Hotel Upgrades
The best renovation period depends on your property’s actual booking patterns. Renovating during lower-demand weeks can reduce lost room revenue and limit disruption to paying guests.
However, there is no single off-season that applies to every hotel.
Peak Travel Seasons
Renovating during peak demand can be expensive because taking rooms out of service reduces available inventory. Construction noise, dust, and closed amenities may also affect guest satisfaction.
Busy periods differ by location and hotel type. A beach resort may depend on summer visitors, while a ski hotel may have its highest demand during winter.
Convention hotels can experience strong demand around large meetings and events, even outside typical vacation seasons.
If renovation must continue during a busy period:
- Separate construction floors or wings from occupied areas.
- Schedule noisy work during approved hours.
- Keep worker access and deliveries away from guest routes.
- Protect corridors, elevators, and nearby rooms.
- Coordinate room availability with the front desk and sales teams.
- Inform affected guests about significant amenity closures before arrival.
Careful coordination helps the property continue operating while protecting guest safety and comfort.
Off-Peak Maintenance Opportunities
Lower-demand periods can offer better opportunities for disruptive renovations. Hotels may be able to close an entire wing or several floors with less impact on expected room revenue.
These periods can also make it easier to schedule utility shutdowns, inspections, contractor access, and deliveries.
Still, off-peak construction does not guarantee lower labor or material prices. Product lead times, contractor availability, and the planned reopening date also matter.
Compare the financial impact of different renovation schedules using expected occupancy, room rates, construction costs, and lost operating contribution.
Accessibility, Code, and Safety Requirements
Hotel renovations must comply with the building and safety rules that apply to the property. Requirements can include accessibility, fire protection, electrical systems, plumbing, ventilation, and environmental controls.
The U.S. Department of Justice ADA Standards for Accessible Design explain the accessibility framework used for covered buildings and alterations.
For lodging properties, the 2010 ADA Standards, including Sections 224 and 806, address accessible guestrooms and their features.
For example, under the new-construction scoping table, a hotel with 76 to 100 guestrooms requires five guestrooms with mobility features, including one with a roll-in shower. It also requires nine guestrooms with communication features, subject to the standards’ rules on overlap and dispersion.
Alterations have their own scoping provisions. The number and type of rooms affected by the project can change how the requirements apply.
Accessibility reviews may cover:
- Guestroom entry doors and clearances
- Bathroom layouts and fixtures
- Accessible routes and turning spaces
- Controls, switches, and hardware
- Communication features
- Room-type choices and dispersion
- Common-area access
These requirements should be considered during design, not after the renovation is nearly complete.
Older buildings may also contain materials that require special handling during demolition.
The U.S. Environmental Protection Agency’s asbestos guidance explains responsibilities for owners and managers of buildings that contain asbestos.
The EPA’s asbestos NESHAP requirements also address inspections and work practices for covered renovation and demolition projects.
Construction activities involving lead may fall under the OSHA construction lead standard, 29 CFR 1926.62.
Warning: Do not begin destructive work based only on a visual estimate. Qualified professionals should assess suspected hazardous materials and determine the testing, permits, safety measures, and accessibility requirements that apply to your property.
Why Sustainable Upgrades Matter in Hospitality
Energy-efficient hotel renovations can lower utility expenses and improve maintenance performance. The savings depend on existing equipment, building condition, guest behavior, and installation quality.
Lighting is one area worth reviewing because hotels use it throughout guestrooms, corridors, public spaces, and back-of-house areas.
According to ENERGY STAR’s lodging energy guidance, lighting accounts for almost one-quarter of electricity use in a typical hotel, excluding its effect on cooling.
The guidance states that lighting retrofits can reduce lighting electricity use by 50% or more, depending on the original system. This is a potential reduction in lighting electricity consumption, not a guaranteed reduction in total hotel utility expenses.
Energy savings should be measured against the property’s actual operating baseline, not promised as a fixed percentage of total costs.
Renovation measures worth evaluating include:
- LED lighting and suitable lighting controls
- Efficient heating and cooling equipment
- Occupancy-based guestroom temperature controls
- Low-flow plumbing fixtures that maintain guest comfort
- Improved insulation and air sealing
- Durable and repairable flooring and furniture
- Materials with lower maintenance needs
- Construction-waste sorting and material reuse
Before approving an upgrade, compare its installed cost, expected service life, maintenance needs, and projected savings.
Also review available rebates or incentives with qualified energy and tax professionals. Incentive availability and eligibility depend on the project and applicable rules.
How to Calculate Hotel Renovation Return on Investment
Hotel renovation return on investment depends on the project’s cost and the additional financial benefit it produces. A better-looking property does not automatically generate enough extra income to recover its cost.
Potential benefits include:
- Higher average daily room rates, if market demand supports them
- Improved occupancy, where achievable
- Lower energy and water expenses
- Reduced repair and maintenance costs
- Fewer rooms unavailable because of equipment failures
- Improved compliance with required brand standards
Start by estimating the difference between the property’s expected performance with and without the renovation.
Then calculate the additional operating expenses needed to support any expected revenue increase.
Simple Payback Calculation
A simple payback calculation estimates how long it may take to recover renovation spending through additional annual cash flow.
Simple payback period = total renovation investment ÷ annual incremental cash flow.
Use a realistic estimate of the cash benefit after additional operating costs, rather than relying on increased room revenue alone.
For a more complete investment analysis, evaluate the timing of cash flows, financing, future replacement costs, and the property’s expected value. A discounted cash-flow model can help compare these outcomes.
If you are evaluating the property’s operating return without financing, separate debt costs from operating performance. If you are evaluating the owner’s cash return, include the relevant financing cash flows.
Use conservative assumptions and compare the renovated property against a realistic unrenovated forecast.
Crafting Your Renovation Budget: A Step-by-Step Guide
A reliable hotel renovation budget starts with a clear scope and accurate room measurements. It should then account for construction, furniture, professional costs, and operational disruption.
Follow these steps to organize your project before awarding contracts.
- Define the project objective: Identify whether the renovation addresses property condition, brand compliance, guest experience, accessibility, operating efficiency, or repositioning.
- Document every room type: Measure standard guestrooms, suites, connecting rooms, and accessible rooms separately.
- Inspect building conditions: Review plumbing, electrical systems, HVAC, waterproofing, subfloors, ceilings, walls, and signs of moisture damage.
- Confirm project requirements: Combine owner priorities, brand standards, accessibility requirements, code obligations, and deferred maintenance.
- Prepare drawings and specifications: Define materials, installation methods, layouts, and expected quality before requesting bids.
- Create a quantity schedule: Count required furniture, fixtures, finishes, hardware, equipment, and spare materials by room type.
- Estimate all project expenses: Include construction, FF&E, professional services, permits, freight, warehousing, installation, taxes, and operational losses.
- Add a controlled contingency: Set a reserve based on building age, concealed-condition risks, inspection quality, and project complexity.
- Approve a model room: Test appearance, clearances, durability, housekeeping access, installation details, and required brand approval.
- Monitor costs during construction: Track contracts, purchase orders, changes, invoices, remaining risks, and the forecast final project cost.
How to Calculate Your Total Renovation Budget
Start with the expected cost per guestroom and multiply it by the number of rooms being renovated.
Initial guestroom cost = number of guestrooms × estimated cost per key.
For example, using the illustrative midscale full-renovation range of $15,000 to $35,000 per key, a hypothetical 100-room project would produce an initial room-and-bathroom estimate of $1.5 million to $3.5 million.
This calculation is an example, not a quote or a verified national construction average. Actual costs depend on the scope and the bids received.
Next, include other costs that are not already included in the per-key estimate.
Total project budget = guestroom construction and FF&E + other property work + professional and compliance costs + procurement and logistics + operational impact + contingency.
Do not add the same expense twice. For example, if freight and installation are included in the guestroom estimate, they should not be added again as separate costs.
If your project includes a lobby, corridors, exterior work, or major building systems, estimate those items separately before calculating the complete renovation budget.
How to Compare Hotel Renovation Bids
The lowest hotel renovation bid is not always the least expensive option. Contractors may use different allowances, schedules, and exclusions, making their proposals difficult to compare.
Prepare a bid comparison sheet that includes:
- Scope of work included and excluded
- Material specifications and quantities
- Allowances and unit prices
- Demolition and disposal costs
- Permit fees and inspections
- Night or weekend work
- Site supervision and project management
- Temporary protection and dust control
- Freight, storage, delivery, and installation
- Expected construction schedule
- Rooms renovated during each phase
- Warranty coverage and completion requirements
- Insurance, licensing, and relevant hotel renovation experience
Ask bidders to identify every exclusion in writing. An omitted bathroom package, freight allowance, or temporary-protection cost can exceed the apparent savings from a lower proposal.
Also review whether the contractor can work safely in an occupied hotel and deliver the project within the required operating schedule.
Before signing, confirm how changes will be priced, who approves additional work, and how completion and defects will be handled.
Frequently Asked Questions
What is the 30% rule for hotel renovations?
There is no universal rule requiring a hotel renovation budget to equal 30% of projected revenue. Owners should assess the complete project cost, financing, property value, required brand improvements, and expected financial returns. A budget should reflect the property’s actual needs rather than an unsupported percentage rule.
How much does it cost to furnish a hotel room?
Furnishing a hotel room can cost several thousand dollars to tens of thousands of dollars, depending on the property tier and specifications. The total varies with furniture quality, custom work, mattresses, lighting, artwork, window treatments, freight, taxes, and installation. Always confirm exactly which items the furniture package includes.
Do hotel upgrades cost money?
Yes. Renovating a hotel’s guestrooms requires spending on materials, labor, design, and often room downtime. However, this differs from a guest receiving a complimentary upgrade to a better room category at check-in. A guestroom-category upgrade is an operating decision, while a renovation improves the physical property.
What is the difference between a soft-goods refresh and a full renovation?
A soft-goods refresh mainly updates visible finishes and movable items, including paint, flooring, bedding, curtains, and upholstery. A full renovation can also replace built-in furniture, lighting, doors, electrical components, technology, and mechanical systems. Bathroom reconstruction may be included, but the exact scope must be stated in the estimate.
How often should hotel rooms be renovated?
There is no single renovation schedule for every hotel. Timing depends on guestroom wear, brand standards, maintenance history, product durability, market expectations, and available capital. Regular inspections help owners plan smaller updates before widespread damage or poor room conditions make larger renovations necessary.
How much contingency should a hotel renovation budget include?
The appropriate contingency depends on the project’s risk and the quality of the initial investigation. Older properties with concealed plumbing, structural damage, moisture problems, or hazardous-material concerns may require larger reserves. Set the amount with your cost estimator and use it only for approved changes or genuine unknown conditions.
Conclusion
Hotel room renovation costs depend on the property’s condition, hotel tier, project scope, and construction requirements. Limited updates may require a relatively small investment, while extensive luxury renovations can reach six figures per room.
Start with a detailed condition assessment and a clearly defined scope. Then obtain comparable contractor bids, include hidden and operational costs, approve a model room, and build a contingency based on actual project risks. A complete property-specific estimate is more reliable than a single national cost figure.
Sources
- Nehmer and HVS Design 2026 Hotel Cost Estimating Guide — publication information and renovation cost categories by property tier and project area.
- Nehmer Hotel Cost Estimating Guide access page — official request form for the complete cost guide.
- U.S. Department of Justice ADA Standards for Accessible Design — official accessibility standards for covered buildings and alterations.
- 2010 ADA Standards for Accessible Design — transient lodging guestroom requirements, including Sections 224 and 806.
- U.S. Environmental Protection Agency asbestos guidance — responsibilities for owners and managers of buildings containing asbestos.
- EPA Asbestos National Emission Standards for Hazardous Air Pollutants — inspection requirements and work practices for covered demolition and renovation activities.
- Occupational Safety and Health Administration lead standard — occupational lead-exposure requirements for construction activities.
- ENERGY STAR lodging energy guidance — hotel energy consumption, lighting efficiency, and related improvement opportunities.